Media Player Los Gigantes!

Author Topic: Monthly update of major work in Los Gigantes  (Read 1101 times)

0 Members and 1 Guest are viewing this topic.

Offline Dolly Diver

  • Administrator
  • Sr. Member
  • *
  • Posts: 1454
1st October 2018 work commenced on the refurbish of Los Gigantes

This topic will be updated every month with the progression of the work

The work is now into the second month and at peak times the traffic lights on the marina road are causing traffic jams which often tail back to Calle El Pino.  It is advisable not to bring your car to the marina unless it is absolutely necessary, its best to park elsewhere and walk.
« Last Edit: December 18, 2018 by Dolly Diver »

Offline Dolly Diver

  • Administrator
  • Sr. Member
  • *
  • Posts: 1454
Re: Monthly update of major work in Los Gigantes
« Reply #1 on: January 27, 2019 »
Work started 1.10.18

Now into 4th month

The new pipes are now in but by the looks of it there is still a lot of work to be done before this section of road is open again.  The traffic light system to enter the marina is still in operation.  This works well but can still be frustrating for drivers at peak times.

Picture 1.  View from Tamara looking down to the marina

Picture 2.  View looking towards Tamara restaurant.

Click on pic to enlarge

Offline Dolly Diver

  • Administrator
  • Sr. Member
  • *
  • Posts: 1454
Re: Monthly update of major work in Los Gigantes
« Reply #2 on: February 27, 2019 »
Work started 1.10.18

Now into 5th month

There is a big visible difference this month.  The barriers have moved another 50 metres up the road.  Tamara restaurant is not accessible so has closed for 1 month.  The road over the new pipe has a temporary surface but is not open to traffic yet.  The new pedestrian way has been started and will be level with the road.

Pic 1  View of the works in front of Tamara restaurant

Pic 2  View of new road surface

Pis 3  Tiles of the new pedestrian way

Clic of pic to enlarge